§ 60.120. Applicability and designation of affected facility.
82 words·~1 min read·
/us/cfr/t40/s§ 60.120·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
(a)The provisions of this subpart are applicable to the following affected facilities in secondary lead smelters: Pot furnaces of more than 250 kg (550 lb) charging capacity, blast (cupola) furnaces, and reverberatory furnaces.
(b)Any facility under paragraph
(a)of this section that commences construction or modification after June 11, 1973, and on or before December 1, 2022, is subject to the requirements of this subpart. [42 FR 37937, July 25, 1977, as amended at 88 FR 80610, Nov. 20, 2023]
Connections6 cite this
Cited by 6 sections · top 3
Citation graph
cites case law
§ 60.120
Applicability and designation of affected facility.
Fed. Reg.×6
Cites 0Cited by 6 across 1 source